For More Information Contact:
Alana Sawchuk, Executive Assistant to the Comptroller
asawchuk@dutchessny.gov / comptroller@dutchessny.gov
845-486-2050
The Dutchess County Comptroller’s Office has completed a special follow-up financial report summarizing the Justice & Transition Center (JTC) capital project as of June 30, 2022. The previous report had covered project accounting as of June 30, 2021.
The jail portion of the capital project is 78% complete with an estimated project close-out in July 2024. This completion date has been extended by three months due to the emergency housing shelter at 26 Oakley Street in Poughkeepsie requiring prior completion before individuals currently utilizing the PODs can move into the new space. The PODs can then be dismantled, and the jail project completed.
As of June 30, 2022, $165 million has been spent or encumbered on all phases of the project, which includes the Law Enforcement Center (Sheriff’s Office) as well as the jail. There is a remaining $26.8 million available to spend of the full $192.2 million appropriated and approved. The JTC design was downsized from its original 569-bed design to 328 beds in 2020. The current estimated cost to complete the revised plan is $131.4 million, approximately $22.8 million less than originally appropriated.
“The JTC project is the largest capital project in Dutchess County history,” said Comptroller Lois. “Over the last five years I have been committed to ensuring proper oversight and accountability of all project-related transactions, and consistently reporting to the taxpayers of Dutchess County.”
The Comptroller’s Office thanks the Dutchess County Department of Public Works and Commissioner Balkind for their assistance in reporting this update to the taxpayers of Dutchess County.
The Justice & Transition Center Update report can be found here (.pdf).